The Development of  Arrow Center’s Dream
  • Outline of Phased
  • Development Plan


2
Aerial View in Relation to New Stadium
3
PHASE 1
Renovation and Move
  • Converted existing open warehouse               space into classrooms and Office Space.


  • Moved the Community Living offices and the Respite offices into the new space.
4
PHASE 1
Renovation - Costs

  • Feasibility Study          :  Completed


  • Initial Architect Drawings                       :  Completed


  • Cost of Renovation               :  $400,000
  • Funding Sources          :  Donations –             Current and Future


  • Construction – Cycle (Start – Finish)      :  08/03 - 01/04
5
PHASE 1
Renovation - Benefits

  • Developed warehouse space into usable classroom space toward final project


  • CLS Lease ended 1/31/2004 (12/31/2003 with a one month extension) – This renovation allowed for a new location for CLS & Respite Administration


  • Savings of over $72,000 per year over the last lease rate and an estimated $100,000 per year, or more in 2004 and beyond with any new lease.



6
PHASE 1
Before – Exterior View
7
PHASE 1
After – Exterior View
8
PHASE 1
After – Exterior View
9
PHASE 1
Before - Interior Space
10
PHASE 1
After – Interior View
11
PHASE 1
After – Interior View
12
PHASE 1
Before - Interior Space
13
PHASE 1
After – Interior View
14
PHASE 2
New Building at 3080 Market Street
  • Build new 16,000 square foot building on the 3030 - 3080 Market Street site that will house the Administration Offices and the current Arrow Center Programs on the old site.
15
PHASE 2
New Building at 3080 Market Street
  • Site Survey    :  Requested from                                            City of San Diego


  • Architect Drawings    :  Pending


  • Cost Estimates    :  $3.4 M


  • Funding Sources    :  Cap. Campaign


  • Construction – Start/Completion Cycle    :  6/07 – 12/08


16
PHASE 2
New Building - Benefits

  • Provides 16,000 square feet of state of the art classroom, program and office area.


  • Consolidates Arc, ARROW, ACES, and CLS administrations in a single geographic location.


  • Provides meeting space at the City Chapter site for both the Arc’s use, and for community use .


  • Opens classroom space at North Shores facility for continued consumer program growth by moving the administrative offices to 3030 Market Street.



17
New Building Site Plan
18
New Building Elevations
19
New Building Elevations